Work has slowed down on the boat because I needed to start two others. The remaining projects are small, usually taking 15 minutes to 1/2 an hour.

April 22

Taping exterior seam

1" tape - Note natural curve.

April 23

Trapped air

May 5

Sanded

Fixing above trapped air. New glass patched in.

May 18

Set up for end pour

May 21

hatch hardware

May 27

Spackle trowel to keep from drilling through the side of the boat